The Installation
K Col Track Upgrade
17 -28 January 2020
6 February 2020
17 -28 January 2020
Working on the planking - photo from John Hughes |
On helicopter delivery day, the four-person track
construction team, two FOMF volunteers and a PWS member were taken to K
Col. Apart personal equipment, food and
tools, there was a small generator and a toilet. Then 19 packs of timber were brought it and
left at the locations along the track where needed.
Unfortunately, one spot due to get timber was overlooked,
resulting mismatched loads at some of the following locations. By a stroke of luck, the problem was
overcome by shortening the work on some sections by eliminating components that
only improved walker comfort without compromising the main objective of
protecting the sensitive cushion plants. On the other side of the coin some
environmentally damaged areas close to surplus timber packs could now be
included.
Construction of the planking commenced at midday on that
first day and continued for 12 days. For
the first 5 days two FOMF volunteers helped and another came for the day. The track construction team were first rate
both with the build quality and dedication to the task. They worked in all
weathers, which at times curtailed the use of battery powered tools and worked
long hours from 7:30 in the morning to 5:30 in the afternoon. But it was when they came upon small sections
of track not earmarked for action, that they shone, by suggesting that they
would go and carry timber to the spot for planking to save the area from being
damaged. PWS also had a couple of very
willing and strong staff who walked in and between them worked for three days
on the project.
The work itself involves lot of sawing of 6m lengths of 4x2,
using small chainsaws to make into posts which are then rammed into the earth
to support the planking. Getting these posts in takes quite a bit of effort
with a large weighted mallet and the ground can be rocky with shallow soil
depth or at the other extreme deep and soft requiring 1.5-metre-long
posts. Unfortunately, some of the post
timber was not good enough quality to use and as result about 4 planks had to
be left for another occasion when it was possible to get more posts
delivered. These were delivered to site
during the helicopter visit to bring out waste from construction and equipment.
The weather intervened making it not possible to collect the
track crew on the planned collection date, and they had to walk out. Conditions only became suitable a week later
and even then cloud threatened to disrupt the flight schedule.
That final helicopter flight day had a bonus for Peter and
Greg, who managed to be invited for a visit to Lake Rhona whilst two PWS staff
were delivered there for an inspection of the area and the track. After leaving
them there we were brought back past Mount Field West and through the valley
where the K Col track is situated. After
leaving us there, the helicopter proceeded to lift out all the bags and
equipment.
Comments